The Duke's repairs are now complete and the engine is running at the East Lancashire Railway on Sunday 29th April as part of the testing process before returning to mainline operations.
Many thanks to the East Lancashire Railway for this opportunity.
Showing posts with label loco update. Show all posts
Showing posts with label loco update. Show all posts
Friday, 27 April 2012
Saturday, 14 April 2012
Friday, 13 April 2012
71000 repair update
You will have already read about damage sustained to 71000 at Bury in late February, as a result of a shed yard collision.
The buffer, buffer plank and supporting gussets on the right hand side were damaged. The loco's front end was stripped down for repair by Colin Green and his team at Ian Riley's within days of getting the go-ahead from ELR. Thanks here to Riley and Son, and our engineers for doing the preparation work.
Simon Holroyd
Deputy CME
The photograph shows the right hand outer gusset lower section receiving attention before the upper section is tack welded into place. The gusset sections were formed to the drawing, then some heating and correction applied to make them fit. The picture shows one of Riley's men warming to red heat, jacking, then tightening with temporary bolts, in order to get new bits to line up with old bits. Although the misalignment is minuscule, thick steel plate like this requires quite a bit of effort.
The buffer, buffer plank and supporting gussets on the right hand side were damaged. The loco's front end was stripped down for repair by Colin Green and his team at Ian Riley's within days of getting the go-ahead from ELR. Thanks here to Riley and Son, and our engineers for doing the preparation work.
The buffer plank was bent but straightened out again in Riley's hydraulic press. Both inner and outer right hand support gussets were damaged beyond repair. Drawings were obtained from the NRM, new fabrications made and supplied to Riley’s in kit form, where they were fitted and tack welded together in situ using temporary bolts before removal and finish welding. Getting the gussets right has been the most difficult and time consuming part of the job. Another fitting session followed where all the holes were drilled through, matching the original holes in the frames and plank, and finally reamed in readiness for riveting.
The plank is now riveted back onto the frames via the angle brackets and next week will see left and right gussets riveted back on. Heritage painting have kept everything primed and ready for painting as the job has progressed. The final job will be the damaged buffer and as these are not available off the shelf, so some method of repair will be found, with new parts being manufactured as required. Working on 4472 has allowed me to keep tabs on progress and speed up decision making but, sadly, the work takes time and we have to let people down. Hopefully, within the month the end will be in sight and we will be back out at work.
On a more pleasing note the engineering team has attracted another new recruit. Ben Carr has already made inroads into the never ending jobs list, repairing a number of valves and associated parts - it's good to see so many young people coming on board. In the last year or so, Liam Clairmonte, Andy Quinn, Sara Lygo and Chris Saxon have all been snapped up by the support crew, and all make a difference. These young people all have the skills and motivation to take 71000 through another 40 or so years. If you are bored on a weekend, come and spend a day with us. See what you think!
The plank is now riveted back onto the frames via the angle brackets and next week will see left and right gussets riveted back on. Heritage painting have kept everything primed and ready for painting as the job has progressed. The final job will be the damaged buffer and as these are not available off the shelf, so some method of repair will be found, with new parts being manufactured as required. Working on 4472 has allowed me to keep tabs on progress and speed up decision making but, sadly, the work takes time and we have to let people down. Hopefully, within the month the end will be in sight and we will be back out at work.
On a more pleasing note the engineering team has attracted another new recruit. Ben Carr has already made inroads into the never ending jobs list, repairing a number of valves and associated parts - it's good to see so many young people coming on board. In the last year or so, Liam Clairmonte, Andy Quinn, Sara Lygo and Chris Saxon have all been snapped up by the support crew, and all make a difference. These young people all have the skills and motivation to take 71000 through another 40 or so years. If you are bored on a weekend, come and spend a day with us. See what you think!
Simon Holroyd
Deputy CME
The photograph shows the right hand outer gusset lower section receiving attention before the upper section is tack welded into place. The gusset sections were formed to the drawing, then some heating and correction applied to make them fit. The picture shows one of Riley's men warming to red heat, jacking, then tightening with temporary bolts, in order to get new bits to line up with old bits. Although the misalignment is minuscule, thick steel plate like this requires quite a bit of effort.
Monday, 19 March 2012
Thursday, 15 March 2012
Duke Buffer Repairs
Following the slight collision on 26th February, work has now commenced to repair the damaged buffer beam, right hand buffer and damaged buffer beam supports. The work is being carried out by Ian Riley Engineering at Bury and should be completed within 3 weeks including repaint.
Friday, 9 March 2012
71000 Schedule Update
Phoenix Heritage Rail Ltd has withdrawn 71000 Duke of Gloucester from the West Somerset Railway Spring Steam Gala on March 17th/18th and March 22nd to 25th.
The damage sustained as a result of a collision in the yard at the East Lancashire Railway on Sunday 26 February is still being assessed with a view to an appropriate programme of repairs being undertaken as soon as possible.
Updates will be posted here as further information becomes available.
Updates will be posted here as further information becomes available.
Monday, 27 February 2012
71000 withdrawn from Steam Dreams March charter
Phoenix Heritage Rail Ltd has withdrawn 71000 Duke of Gloucester from Steam Dreams London-Plymouth-London charter with 60163 Tornado on March 10th. Until investigations have been conducted regarding damage sustained during an incident at the East Lancashire Railway on Sunday 26th February it not possible say how the rest of the locomotive’s 2012 programme will be affected. Updates will be posted as information becomes available.
Thursday, 23 February 2012
New 71000 numbers unveiled
The new 71000 numbers on the side of the cab are now completed and will be shown for the first time at this weekend's East Lancs Gala.
A new arch has also recently been fitted to the firebox.
Saturday, 11 February 2012
New painted numerals for ELR February Gala
The loco has undergone a repaint this winter, in addition to the heavy workload of annual maintenance. Those who saw the loco at the ELR's Winter Gala will, no doubt, have spotted a slight miss match between the cab and the rest of the engine's Brunswick green paint - this is currently being rectified.
The decision was taken late last year to carry out a traditional brush type repaint and, subject to authorisation by the owning company, a return to painted numerals on the cab side. To paint a big Pacific in winter takes a lot of time and patience and I must thank the East Lancs Railway for their support and pit space during the works, and Ian Riley for use of gantries and scaffolds to allow a safe system of work.
Ian and Gilbert of Heritage Painting have applied approximately 55 litres of primer, undercoat, gloss and varnish over the last two months and the finish is outstanding. As well as repainting all of the gloss green parts of the loco, the buffer planks, piano front, air brake cocks and running board tops have all received attention.
The Duke of Gloucester will be rolled out at the ELR's February Gala, the finished article, complete with painted numerals.
Simon Holroyd.
Friday, 27 January 2012
71000 faces challenge to take part in ELR Gala
Last weekend's ELR Gala threw up a few challenges for the team. We met on Friday night at Bury to test the new systems we have installed over the past few months. Adrian Meakin and his team had the loco ready for testing, with a nice glowing fire and 150psi on the clock. We started the air pump, and within seconds it was clear we had a leak. Gary Shannon crawled in and traced it to a new fitting on the "wet tank" outlet. A couple of attempts to secure it failed so we had to remove the whole pipe - tricky over a pit with plenty of light but damn near impossible outside with torches and no pit, but we managed.
It was a faulty cone fitting so we had to remove it and braze on a new one with more struggling to refit the pipe. Then another test and another leak but much smaller this time (you can't hear the little ones till you fix the big ones). This one was in the steel pipe from the compressor head to the aftercooler. There are a number of joints which I welded, two of them had a pin hole in them. Devastated, we removed this pipe too, calling time on the night's activities at 9.30 pm. We still had to move the engine after explaining we would not be ready first thing in the morning. The three of us trudged into the Trackside at 10pm and instantly cheered up!
An early start saw us waiting for one of Riley's welders to turn up to repair the pipe as the ELR's machine burst into flames welding our tender tank the week before. A two hour wait and no sign of Riley's man meant I would have to weld it again. Of course, we had to obtain permission to use one of Riley's machines so another wait then! Now with the new spirit of cooperation we enjoy, not only can we use Riley's welding machine, but also his benches and grinder!
Obviously I carried out my best weld ever, and when we tested it, first with dye penetrant fluid, then on the engine, no leaks were found.
So, ready to go then? No, not quite. A full brake test found a steam leak from the small ejector vacuum pipe inside the 'S' bend between the duplex valve and the boiler trunking, half way up the left side of the firebox. Investigation found the pipe to be fractured due to fatigue. This pipe is very long and expands around 3/4 inch in length when you open the steam valve, all of the expansion is taken up in the 'S' bend, just a matter of time then. With little hope of having a suitable length of 7/8 inch steam pipe, joints and cone fittings, we had to fail the engine. It was late morning, and none of us having had any breakfast, we were pretty low by this time. While I went off in search of food, Gary and Liam went in search of copper pipe and fittings which amazingly they found!
Next job with the loco in the shed, smoking it out, Liam removed the rearmost trunking section (not pleasant when it's just been beautifully painted) to find a joint section, about a foot in from the offending bend, with this split with some oxy-acetylene, a new section could be made. We bent the new pipe to match, brazed the new cone on, which is required to screw the pipe end to the duplex valve. Derek Turner machined the joint coupling on the lathe, and when this was finished, Gary and I brazed the new pipe on in situ, wobbling around on ladders, half way up the boiler. A quick test with steam proved the repair to be sound Another half hour fiddling saw the trunking back on. A further half hour saw our loco off shed and away to take the 16.05pm train to Ramsbottom. A fantastic sight and a fantastic effort, thanks to all involved.
Simon Holroyd, Deputy CME
It was a faulty cone fitting so we had to remove it and braze on a new one with more struggling to refit the pipe. Then another test and another leak but much smaller this time (you can't hear the little ones till you fix the big ones). This one was in the steel pipe from the compressor head to the aftercooler. There are a number of joints which I welded, two of them had a pin hole in them. Devastated, we removed this pipe too, calling time on the night's activities at 9.30 pm. We still had to move the engine after explaining we would not be ready first thing in the morning. The three of us trudged into the Trackside at 10pm and instantly cheered up!
An early start saw us waiting for one of Riley's welders to turn up to repair the pipe as the ELR's machine burst into flames welding our tender tank the week before. A two hour wait and no sign of Riley's man meant I would have to weld it again. Of course, we had to obtain permission to use one of Riley's machines so another wait then! Now with the new spirit of cooperation we enjoy, not only can we use Riley's welding machine, but also his benches and grinder!
Obviously I carried out my best weld ever, and when we tested it, first with dye penetrant fluid, then on the engine, no leaks were found.
So, ready to go then? No, not quite. A full brake test found a steam leak from the small ejector vacuum pipe inside the 'S' bend between the duplex valve and the boiler trunking, half way up the left side of the firebox. Investigation found the pipe to be fractured due to fatigue. This pipe is very long and expands around 3/4 inch in length when you open the steam valve, all of the expansion is taken up in the 'S' bend, just a matter of time then. With little hope of having a suitable length of 7/8 inch steam pipe, joints and cone fittings, we had to fail the engine. It was late morning, and none of us having had any breakfast, we were pretty low by this time. While I went off in search of food, Gary and Liam went in search of copper pipe and fittings which amazingly they found!
Next job with the loco in the shed, smoking it out, Liam removed the rearmost trunking section (not pleasant when it's just been beautifully painted) to find a joint section, about a foot in from the offending bend, with this split with some oxy-acetylene, a new section could be made. We bent the new pipe to match, brazed the new cone on, which is required to screw the pipe end to the duplex valve. Derek Turner machined the joint coupling on the lathe, and when this was finished, Gary and I brazed the new pipe on in situ, wobbling around on ladders, half way up the boiler. A quick test with steam proved the repair to be sound Another half hour fiddling saw the trunking back on. A further half hour saw our loco off shed and away to take the 16.05pm train to Ramsbottom. A fantastic sight and a fantastic effort, thanks to all involved.
Simon Holroyd, Deputy CME
Saturday, 21 January 2012
New spark arrestors fitted
Fire risk, caused by sparks from the chimney and hot cinders from the ashpan, has been a problem that has existed since steam motive power became a reality.
Fortunately, the Duke lends itself to being covered underneath by various types of meshes so the risk of fire from the ashpan through hot cinders is not a big issue.
To prevent the emission of sparks from the chimney the Duke has a dual spark arrestor system fitted around the chimney assembly to attempt to ensure that any particles passing through the arrestor would be so small as to not start a lineside fire.
The meshes on the Duke's arrestors are now being replaced after 8 years of good service.
Support crew member Ken Wilcock has already completed one of the two interlocking screens and is now on with the second.
Monday, 16 January 2012
ELR launch for newly painted Duke
71000 Duke of Gloucester has spent its entire life in preservation, painted in two pack acrylic spray paint. The first time this was done in the late 80s, the finish was very durable and looked superb. A repaint in 2004 was not such a success with the loco starting to look rather tatty, so we decided on a partial repaint to see us through to the end of the engine's ticket. This time it is being brush painted like it was in BR service - only better! The boiler, running boards, buffer planks, piano front and tender have all received attention.
The work has been entrusted to Ian Hewitt and his team at Heritage Painting who have battled the elements over the Christmas period to get the job done, with the deadline for completion being the January 21st/22nd Winter Steam Gala at the East Lancs Railway. The finish is superb, better than we could have ever hoped for and, whilst not quite finished as I write this, we are very exited at the prospect of seeing the finished article next week in the sunlight, as we prepare for a weekend's running.
See you there
Simon Holroyd, Deputy CME
The work has been entrusted to Ian Hewitt and his team at Heritage Painting who have battled the elements over the Christmas period to get the job done, with the deadline for completion being the January 21st/22nd Winter Steam Gala at the East Lancs Railway. The finish is superb, better than we could have ever hoped for and, whilst not quite finished as I write this, we are very exited at the prospect of seeing the finished article next week in the sunlight, as we prepare for a weekend's running.
See you there
Simon Holroyd, Deputy CME
Wednesday, 24 August 2011
Locomotive update - 23rd August 2011
After a period of running on the West Somerset Railway, 71000 Duke of Gloucester returned to Bristol Barton Hill depot on Thursday 18th August and resumed Torbay Express duties on Sunday 21st August. This was the Duke’s first main line run since a reportable incident on 12th June 2011.
The load for 71000’s “Torbay Express” run on 21st August comprised 12 coaches + POB + Class 47 diesel. 71000 performed exceptionally well throughout with no mechanical defects reported and arrived ahead of booked time at several points en route. Diesel assistance was required on the climb at Churston but for the remainder of both outward and return legs the diesel was shut down.
71000 engineers have now conducted extensive testing of the locomotive’s valve gear and associated components but have been unable to identify any fault which may have contributed to the incident on 12th June. Controlled tests and running at the West Somerset Railway also confirmed the locomotive to be in sound mechanical condition. Unfortunately, to date, all of the tests conducted by 71000 Trust engineers have failed to identify an assignable cause for the problems experienced on 12th June.
71000’s next main line operation will be a Pathfinder Tours run Bristol-Carmarthen-Bristol on Monday 29th August.
Following 71000’s last Torbay operation on Sunday 4th September, the locomotive will move by rail to Nene Valley Railway at Wansford to appear at a steam gala on Saturday 10th and Sunday 11th September.
71000 is expected to remain at NVR with workings until end of September/early October.
After what has been a difficult summer for 71000 support crew, Phoenix Heritage Rail Ltd wishes to thank Paul Conibeare, Andrew Forster and their staff for assistance and use of facilities at the West Somerset Railway. Also sincere thanks to all who have sent messages of support wishing a speedy return to main line duties for 71000 Duke of Gloucester.
Further information regarding future movements will be found on the 71000 Trust website.
David Briggs Chairman, Phoenix Heritage Rail Ltd.
Further information regarding future movements will be found on the 71000 Trust website.
David Briggs Chairman, Phoenix Heritage Rail Ltd.
Monday, 1 August 2011
Locomotive update
71000 Duke of Gloucester has now completed 560 miles of running in on the West Somerset Railway. Tests carried out at Bristol Barton Hill and WSR running have shown there to be no mechanical defects with the locomotive.
71000 will return to Torbay Express duties as stand by locomotive for King Edward 1 on Sunday 7th August. Should the Duke not be called upon for Torbay duties, it will attend West Somerset Railway Association’s Vintage Rally, in light steam, at Norton Fitzwarren on Saturday 6th and Sunday 7th August.
From Thursday 4th August, 71000 will be based at Bishops Lydeard and the locomotive’s next scheduled WSR steaming will be a footplate experience course on Saturday 13th August. On Sunday 21st August, 71000 will resume as scheduled locomotive for the Torbay Express.
David Briggs
Chairman, Phoenix Heritage Rail Ltd.
71000 will return to Torbay Express duties as stand by locomotive for King Edward 1 on Sunday 7th August. Should the Duke not be called upon for Torbay duties, it will attend West Somerset Railway Association’s Vintage Rally, in light steam, at Norton Fitzwarren on Saturday 6th and Sunday 7th August.
From Thursday 4th August, 71000 will be based at Bishops Lydeard and the locomotive’s next scheduled WSR steaming will be a footplate experience course on Saturday 13th August. On Sunday 21st August, 71000 will resume as scheduled locomotive for the Torbay Express.
David Briggs
Chairman, Phoenix Heritage Rail Ltd.
Monday, 25 July 2011
Locomotive update
On Wednesday 20th July, 71000 Duke of Gloucester and POB were towed in light steam with a DBS class 66 diesel from Bristol Barton Hill depot (via Westbury) to Bishops Lydeard on the West Somerset Railway. During the move 71000 was tested under load and no problems found. Further testing was carried out with light engine running between Bishops Lydeard and Norton Fitzwarren and the locomotive found to be in sound working order.
On Saturday 23rd July the Duke entered service on the West Somerset Railway and will haul trains daily up to and including Friday 29th July. Early indications confirm the locomotive to be in good working order. Depending on outcomes from this running-in period, the length of stay at WSR will be reviewed. It is hoped that 71000 will return in August to complete main line commitments with Torbay Express Limited and Pathfinder Tours. The cause of 71000’s failure on 12th June whilst hauling the Torbay Express remains under investigation.
David Briggs
Chairman, Phoenix Heritage Rail Ltd
On Saturday 23rd July the Duke entered service on the West Somerset Railway and will haul trains daily up to and including Friday 29th July. Early indications confirm the locomotive to be in good working order. Depending on outcomes from this running-in period, the length of stay at WSR will be reviewed. It is hoped that 71000 will return in August to complete main line commitments with Torbay Express Limited and Pathfinder Tours. The cause of 71000’s failure on 12th June whilst hauling the Torbay Express remains under investigation.
David Briggs
Chairman, Phoenix Heritage Rail Ltd